Test case #62630
Tripnet F+H over all verification
Status: | Closed | Start date: | 04/09/2019 | ||
---|---|---|---|---|---|
Priority: | Normal | Due date: | 04/11/2019 | ||
Assignee: | Ninu Laiza D'Silva | % Done: | 20% | ||
Category: | Test Case | Estimated time: | 24.00 hours | ||
Target version: | - | Spent time: | 8.00 hours | ||
End_Date: | Initial Planned Hours: | 24 | |||
remarks: |
Description
1.Verify entire B2B concept
2.Menu Permission,User creation,Debit/Credit balance on different currency etc
3.Verify all reports
History
#1 Updated by Arun S about 6 years ago
- Due date set to 04/11/2019
- Estimated time set to 24.00
- End_Date deleted (
04/09/2019) - Initial Planned Hours changed from 0 to 24
#2 Updated by Ninu Laiza D'Silva about 6 years ago
- Status changed from New to In Progress
#3 Updated by Ninu Laiza D'Silva about 6 years ago
- % Done changed from 0 to 20
verifing F+H module.Following bugs posted.
62712 Improvement New F+H | Pop up heading
62709 Bug New TQR not working |for all property
62704 Bug New F+H | Ticket page | Blank page issue
62699 Improvement New Fav icon issue
#4 Updated by Ninu Laiza D'Silva about 6 years ago
- Status changed from In Progress to On hold
QA rejected on same date due to major issues found in publish.
#5 Updated by Arun S almost 6 years ago
- Status changed from On hold to Closed